解题报告
题意:
工厂有m台机器,须要做n个任务。对于一个任务i。你须要花费一个机器Pi天,并且,開始做这个任务的时间要>=Si,完毕这个任务的时间<=Ei。
对于一个任务,仅仅能由一个机器来完毕。一个机器同一时间仅仅能做一个任务。
可是,一个任务能够分成几段不连续的时间来完毕。问,是否能做完所有任务。
思路:
网络流在于建模,这题建模方式是:
把每一天和每一个任务看做点。由源点到每一任务。建容量为pi的边(表示任务须要多少天完毕)。
每一个任务到每一天,若是能够在这天做任务,建一条容量为1的边。最后。把每天到汇点再建一条边容量m(表示每台机器最多工作m个任务)。
#include
Task Schedule
Time Limit: 2000/1000 MS (Java/Others) Memory Limit: 65536/32768 K (Java/Others) Total Submission(s): 3311 Accepted Submission(s): 1154 Problem Description
Our geometry princess XMM has stoped her study in computational geometry to concentrate on her newly opened factory. Her factory has introduced M new machines in order to process the coming N tasks. For the i-th task, the factory has to start processing it at or after day Si, process it for Pi days, and finish the task before or at day Ei. A machine can only work on one task at a time, and each task can be processed by at most one machine at a time. However, a task can be interrupted and processed on different machines on different days. Now she wonders whether he has a feasible schedule to finish all the tasks in time. She turns to you for help.
Input
On the first line comes an integer T(T<=20), indicating the number of test cases. You are given two integer N(N<=500) and M(M<=200) on the first line of each test case. Then on each of next N lines are three integers Pi, Si and Ei (1<=Pi, Si, Ei<=500), which have the meaning described in the description. It is guaranteed that in a feasible schedule every task that can be finished will be done before or at its end day.
Output
For each test case, print “Case x: ” first, where x is the case number. If there exists a feasible schedule to finish all the tasks, print “Yes”, otherwise print “No”. Print a blank line after each test case.
Sample Input
2 4 3 1 3 5 1 1 4 2 3 7 3 5 9 2 2 2 1 3 1 2 2
Sample Output
Case 1: Yes Case 2: Yes
Author
allenlowesy
Source